Internal Report · Project Controls

VERVE – CITY WALK PHASE 4

Programme performance · Data date 2026-10-13 · Longest path & KPI analysis

Schedule position

-45d

Reported to Client · Tower A L4 slab progress

Schedule slip

45days

Behind approved programme

Longest path analysis

20

Driving completion & milestones

Delayed procurement packages

29

Packages behind plan at any stage

Delayed items logged

144

Civil & MEP, mock-up and main works

Duration & Progress Status

Weekly progress report · cut-off 13-Oct-26

31.1%Time elapsed293 / 943 d

Overall progress

Commencement25-Dec-25
Contractual completion24-Jul-28
Forecast completion07-Sep-28
Overall project delay45 d

Weekly progress · 13-Oct-26

Manpower · Oct 26

Schedule Comparison

Planned vs actual progress by key stage (%)

PlannedActual
Mock up100%vs99.99%
Planned 100%Actual 99.99%
Start Up Shop Drawings93.89%vs79.63%
Planned 93.89%Actual 79.63%
Engineering & Procurement16.85%vs21.08%
Planned 16.85%Actual 21.08%
Construction14.89%vs13.05%
Planned 14.89%Actual 13.05%
Handing Over0%vs0%
Planned 0%Actual 0%

Progress Variance

This-week variance by area — positive is ahead of plan

Project Control Milestone Status

Contract milestones vs forecast finish

Control milestoneMonthsPlanned finishForecast finishVariance
Completion of Substructure works including grade on slab for towers0624-Jun-2620-Jun-26 A+4d
Completion of off-site mockup0824-Aug-2609-Sep-26 A-16d
Completion of engineering / procurement works15.509-Apr-2720-May-27-40d
Completion of first in place apartment1624-Apr-2702-Jul-27-69d
Completion of super structure works for towers17.510-Jun-2723-Jul-27-43d
Completion of MEP T&C (2B+G+2B+G+L1~L14)2222-Oct-2717-Dec-27-56d
Completion of MEP T&C (L15 to Roof) (24.5M)24.510-Jan-2810-Mar-28-60d
Completion of the consultant snagging /desnagging (2B+G+L1~L14)26.510-Mar-2824-Apr-28-45d
Completion of consultant snagging/desnagging (L15 to Roof)28.510-May-2823-Jun-28-44d
Completion of all authorities' completion certificates (BCC)3023-Jun-2808-Aug-28-46d
Completion of employer snagging/desnagging (2B+G+2B+G+L1~L14)3023-Jun-2808-Aug-28-46d
Completion of employer snagging/desnagging (L15 to Roof)3110-Jul-2823-Aug-28-44d